After almost a decade of negotiations and planning, the Town of Milton has secured a significant breakthrough in the Hourglass Project saga, signaling a step forward for the redesign of a busy intersection.
Conceived as a response to the hazardous intersection of Route 7, Railroad Street and Middle Road, the Hourglass Project has been a focal point of Milton's infrastructure efforts for years.
Originally aimed at enhancing safety and fostering economic growth, the project has encountered many obstacles, primarily centered around land acquisition from the Papaseraphim family.
However, recent developments have brought renewed optimism as the town successfully negotiated with the Papaseraphims to purchase the entire 4.5-acre parcel of land for $2,450,000.
This land, to be used for the Southern Leg portion of the project, includes various properties, including an old restaurant, three mobile home units and undeveloped acreage.
Town Manager Don Turner told the Independent the deal is a significant achievement. He is also proud to have helped the residents of the property transition to new spaces.
"It was very reassuring to meet with them, explain how we could help and then have it all turn out as we told them," he said. “I'm very thrilled that we were able to make that all happen with as little stress as possible for any of them. That was an essential part of keeping the project moving forward.”
The town's next steps include auctioning off the mobile homes to generate more funds for the project, checking the former restaurant for asbestos before tearing it down and building the gravel portion of the connecting road.
Turner also said the power company’s 50-foot wide easement on the property will need to be eliminated by putting the power underground at the new intersection.
All the money that has been used and will be used for that project is already in the town's possession, Turner said. In 2018, the town secured a loan for the project, which has been paid down by Milton’s Tax Increment Financing district.
"We had just under $8 million when we entered into the contract, of which $2.4 will be used to buy the property and some of the other money will be used to build the project,” Turner said.
Looking ahead, the Town of Milton envisions utilizing the remaining land for downtown development, in line with the community's vision for the area. By collaborating with a developing firm, the town aims to shape the future of its downtown while enhancing the intersection's functionality and safety.
As the town embarks on this next phase of the Hourglass Project, community engagement remains crucial. Turner said the residents are encouraged to participate in ongoing discussions and provide feedback as the project moves forward.
For those interested in learning more or voicing their concerns, the next Selectboard meeting is scheduled for 6 p.m. on April 15, accessible via Zoom or in person at the Municipal Office Building community room, located at 43 Bombardier Road.