During the Oct. 30 Milton selectboard meeting, the board made a key decision for the new Public Work Facility project's development, awarding a construction contract to St. Albans business, Connor Contracting, Inc.
At the recent meeting, Town Manager Don Turner introduced the resolution and discussed crucial aspects of the project with the selectboard. The resolution adheres to the Town of Milton Purchasing Policy, which mandates competitive bidding and Selectboard approval for purchases exceeding $15,000.
This move follows the initial contract awarded to Connor Contracting, Inc. on Oct. 24, 2022, appointing it to oversee preliminary construction management services for the project. Over the past year, the business has worked closely with the project team, architects Wiemann-Lamphere and other experts to create a comprehensive bid package, Turner said.
On Sept. 25, 2023, Connor Contracting shared its final project plans and specifications to qualified subcontractors, with bid submissions due by Oct. 20.
The project team met on Oct. 26 to discuss the total project costs, schedule and any outstanding issues. A site visit was also conducted to verify the Park Place site was prepared as according to project plans.
Connor Contracting reported the total projected costs to construct the building according to final plans and specifications is $4,732,713. Turner mentioned this amount does not include an owners contingency or certain items that have been excluded from the bidding process, such as a salt shed, pavement, generator, storage racks, fencing, appliances, furnishing, flagpole, signage and more miscellaneous items.
Prior to the selecboard’s Oct. 30 decision, the Town of Milton had already invested nearly $1,414,635.76 in the project. This sum includes all permitting, phase one infrastructure work and site preparation carried out by the highway department.
During phase one of the project, Don Weston was awarded roughly $684,323 to complete infrastructure work.
Significant cost savings were also attributed to the efforts of the highway department, led by Milton highway superintendent Eric Gallas and his team. While the budget for sidewalk work was set at $1.3 million, the highway department and its work was able to bring the cost down to approximately $250,000.
“So I will say it thanks to his (Gallas) work and his leadership, and the team that they assembled out there, they saved this community $600,000 just in this portion of the project,” Turner said.
Selectboard members Brenda Steady and Darren Adams also took time during the meeting to personally thank Gallas and public works director, Lisa Schaeffler for their work on the project.
“Milton should be very blessed that we have people that can do this,” Steady said.
Residents should expect to see progress on this project in the coming months. The new facility is expected to be occupied by the public works department before the 2024-25 winter season.