Editor's Note: The Milton Independent is a sister newspaper to the Colchester Sun and the Essex Reporter under the O’Rourke Media Group. As neighboring towns that share boarders, representatives and business customers, "The Bigger Picture" is a special Friday series where the journalists of the neighboring papers recommend a story they’ve written that week to be shared on the other sites.
COLCHESTER — The Vermont Agency of Transportation announced last week that it completed its first phase of construction for the Exit 16 Diverging Diamond Interchange.
The project intends to improve the roadway along the U.S. Routes 2 and 7 corridor in the vicinity of Interstate 89 Exit 16 to enhance mobility and safety in Colchester.
The first phase of construction started with the removal of a subsurface ledge by way of hydraulic hammering, drilling and blasting, all of which went on until the end of June. The project then relocated utilities, installed drainage infrastructure and built retaining walls beneath the interstate bridges to make way for a pedestrian and bicycle connection within the new DDI.
This first construction season necessitated around-the-clock construction to reduce impact to the public, as crews restricted blasting activities to daytime hours, and — as nearby residents have likely noticed — significant traffic impacts to nighttime hours.
Though the project’s projected cost will total about $14 million when all is said and done, VTrans considers the solution a cost-effective and relatively low-impact strategy to address traffic and safety concerns with the current interchange — as the DDI fits within the existing footprint of the existing I-89 bridges.
The DDI will modernize traffic signals at South Park Drive, I-18 Exit 16, Mountain View Drive, Hercules Drive and Tigan Street in Winooski; add shared pedestrian and bicycle lanes within the interchange and a concrete sidewalk installation leading up to the interchange on both sides of the roadway; and implement robust pavement marking, raised islands, and ground-mounted and overhead signage and signaling packages to guide drivers safely.
The DDI design decreases the number of difficult left hand turns to be made around the exit, without increasing the number of lanes or traffic signals, according to an informational YouTube video which displays a moving model of what is to come.
This will be accomplished by way of adding left turning lanes to both routes at the Mountain Drive, Hercules Drive and Rathe Road intersection.
The new design will better serve an increasing number of motorists who travel through it daily, as well as better accommodate others who share the road. The existing configuration was built in 1971, but now handles tens of thousands of drivers each day, with current volumes and future projections necessitating a new traffic configuration to improve mobility and safety for all.
There are already 100 DDIs in the U.S. with dozens more planned throughout the country, but this one in Colchester will be Vermont’s first, expected to decrease the number and severity of crashes in the area. Other states with DDIs have reported crash reductions of up to 60%.
Michael LaCroix, VTrans Project Manager for the DDI, said the current interchange experiences significant queuing and motorist delay, resulting in an average of three reported collisions each month — the eight highest accident-rate in the state — many of which involve left-turning traffic.
Currently, accommodating left-turning traffic at signalized intersections requires green time to be taken away from opposing through traffic, and reduces the overall cycle of time to the traffic signal — which in turn creates vehicular delay and an inability to sufficiently handle all traffic at the intersection, he said.
Queuing increases the likelihood of rear-end and side swiping collisions in particular.
The DDI eliminates left turn phases at the traffic signals, by directing both left turning and through moving traffic to the left side of the road, before the drivers’ decision to turn or remain straight occurs at the on-ramps.
Left turning movements from the off-ramps are also unsignalized. Instead, traffic entering and leaving the interstate will now only encounter one traffic signal, instead of two, which will greatly decrease congestion and risk of collisions.
The project area extends from the Colchester-Winooski town line north for about a mile, to just beyond the intersection of Sunderland Woods Road at U.S. 2 and 7.
Although the first phase — which began last winter — is now considered complete, some work will continue on prior to the official start of phase two which will start this upcoming winter. The Project Team anticipates the second and final phase will continue through 2026.
Each phase is being executed under separate contracts.
In the meantime, Vermont Gas Systems will continue conducting independent utility work along the east side of U.S. 2 and 7 between South Park Drive and Mountain View Drive under the closure of the outermost northbound lane.
This VGS work is anticipated to go on for several more weeks, Mondays through Fridays from 6 a.m. until 4 p.m.
The second phase of DDI construction will focus on the bulk of the roadway work, including the actual construction of the soon-to-be interchange, according to a Nov. 24 email from VTrans.
Phase two will also involve the addition of turning lanes at adjacent intersections, upgrades to existing traffic signals and construction of the aforementioned pedestrian and bicycle accommodations.
Now, VTrans is soliciting feedback from community members about the impacts of its construction and its project outreach, to better inform its building and communication practices as it plans to implement phase two and complete the remainder of construction after this winter.
Those interested in supplying VTrans with such feedback may take the survey — which will be open until Dec. 15 — here. The survey is anonymous, and questions asked in the comments section will not receive a response.
Anyone with questions who would like a response is being instructed to email info@Exit16DDI.vtransprojects.vermont.gov. The 24-hour project hotline is 802-595-4399.
During the first phase of construction, VTrans released daily blasting updates on the Exit 16 DDI Project website, as well as several project announcements and traffic alerts related to public meetings, traffic pattern changes and other operations, with the option for alerts.
To register for emailed updates about the upcoming second phase of the project, as well as word of any related upcoming public meetings, fill out the sign up form here.
Additional information can be found in the project fact sheet, in the project brochure, on the interactive project map and on the project website — or those with further questions may read a set of detailed responses to 20 of the public’s most frequently asked DDI questions here.