MILTON – On Friday, Dec. 20 residents of the Milton Mobile Home Co-op celebrated the completion of an infrastructure redevelopment project that was long in the works.
Residents met with representatives from Commonland Solutions (a housing and community development consultant), Senator Sander’s office, Environment Protection Agency, Vermont Department of Environmental Conservation, Department of Housing and Community Development, Housing and Conservation Board and Community Loan Fund.
The 5 million dollar water and wastewater infrastructure project completed this year marked the first time residents have safe drinking and wastewater infrastructure since the co-op purchased its park in 2012.
“This is a really exciting moment,” Principal Consultant at Commonland Solutions, Liz Curry said. “It’s the culmination of six years of work.”
When the co-op purchased the land, Curry said they found problems in the water and wastewater infrastructure and immediately began to work on changes. The co-op went through project development and funding through different state agencies.
The co-op was forced to halt any progress when the COVID-19 pandemic hit and cost of construction rose, soon they were looking at a 1 million dollar gap for funding the project. The project was able to restart thanks to Congressionally directed spending from Sander’s office.
Ethan Hinch, a representative from Sander’s office read remarks from the Senator.
“It's no secret that our nation's infrastructure is crumbling. Until recently, the federal government has chronically underfunded disrepair,” Sanders wrote. “It's unconscionable that so many of our nation's drinking water and wastewater systems are in a state of disrepair. Water is a fundamental human right that should be safe and accessible for all. Period.”
As a former mayor, Hinch said Sanders understands many communities can’t afford the bill to pay for infrastructure repair. Sanders brought in just over $900,000 in funding.
Vermont’s Department of Environmental Conservation Deputy Commissioner Heather Pembroke, said it was a great time to be investing in these projects.
Working with the 99 cooperative homes, she said, is incredible for herself and Vermont. It’s a large number of people that are being affected by this project from now and into the future she added.
“It's this generation, but it's also the next generation,” Pembroke said. “These are generational projects. You're helping, not just the current residents, but everybody into the future. It's so much what we need, and so much we didn’t have.”
The Vermont Community Development Program, a part within the Department of Housing and Community Development, has been involved with the project since 2017.
In 2019 the program awarded the co-op with $700,000, however, at the end of the project the program awarded a total of $850,000 in community development block grants.
“Our maximum award is, up to a million dollars, and we don't really hit that very much,” administrative services manager for the department, Patrick Scheld said. “So $850,000 is a significant contribution from our program, and we're very, very happy.”
Service in infrastructure repair, like the one completed in Milton, plays an important part in fixing the housing shortage Scheld said. It’s a strategy revolving around keeping and preserving current house stock in the state.
Director of the Vermont Housing and Conservation Board, Gus Seelig, agreed with the approach of conserving homes and preserving affordable housing in the state.
“What we see across the state is that our real estate market has changed greatly, and this park will be an island of affordability, even as the average cost last year was more than $600,000,” he said. “Preservation is really important. Preserving affordability is really important.”
With the mobile home lands officially connected to the town’s water and wastewater lines, co-town manager John Bartlett said the completion of this project is almost a second celebration of life for Don Turner.
“He thought of people in this park and elsewhere, not only as people that he was working for, but as neighbors,” Bartlett said. “I know the kind of person he is, this would have meant a lot to him that it was completed, and sorry he can't be here, but certainly we'll continue to partner with the park now that they're customers.”
Already the investments into new infrastructure have paid off as Thomas Elwood, the Water and Wastewater Superintendent told project leads a fire was started in the co-op and stopped from recently installed fire hydrants.