MILTON — Milton residents can expect to see more than just signs of spring in the coming months.
From major road work in the town center to new housing developments, park improvements and business construction, town officials say several projects are expected to take shape across Milton this spring and summer — some already beginning to draw attention.
At the center of it all is the long-awaited Hourglass project, which Town Manager Chris Taylor said is now on the verge of moving from years of planning into visible construction.
“I think the biggest one is kind of, at this point, an obvious one,” Taylor said. “It’s the Hourglass Project here in the center of town. We are right on the cusp of a lot of stuff happening over in that area.”
The Hourglass Project is a long-planned reconfiguration of the U.S. Route 7, Railroad Street and Middle Road area in Milton, designed to improve safety and traffic flow while also creating a new town green. The project includes new traffic signals, additional turning lanes, new road alignments and connector roads, according to the Vermont Agency of Transportation.
Taylor said pre-construction meetings with the Vermont Agency of Transportation and contractors have already taken place, and surveying work is underway. The contractor, Engineers Construction Inc., has already begun staging for the project.
As construction ramps up, residents should also prepare for traffic pattern changes in the area.
“There will definitely be some traffic reconfigurations that are going to happen,” Taylor said.
Construction is expected to begin with the two connector roads — Keelty Crossing and Whisper Lane — before larger work begins along Route 7 later this construction season. Those roads are expected to help redirect traffic around sections of Route 7 while work is underway.
While the bid process listed July 2027 as the end date for construction, Taylor said the goal is to complete most of the major work this season, with only incidental items carrying over into next year.
“So that’s really the biggest project people are going to see, and really the biggest disruption for town, as far as projects,” Taylor said. “But we’re glad it’s here.”
The activity comes as Milton officials are also looking ahead at how the town grows in the years ahead. Earlier this week, the selectboard approved the town’s 2026-2034 Town Plan, which is intended to guide decisions around housing, transportation, infrastructure and development.
“The town plan connects the community values to real-world decisions about how Milton grows,” planning and zoning officer Cassandra LaFayette said during a public hearing on the plan.
Elsewhere in town, residents may have already noticed visible changes near Bombardier Park, where land has been cleared for a new housing development.
Taylor said the O’Brien project is expected to bring roughly 85 housing units to the area once complete, though the current work represents only the first of three phases.
“There’s been a lot of trees being cleared,” Taylor said. “It is a stark contrast to what people are used to seeing over there. So it definitely catches the eye.”
Another housing development, Dogwood Circle, is also continuing to move forward. Taylor said that project is expected to include 32 units, and much of the infrastructure work has already been completed.
The developments reflect both local and regional efforts to address ongoing housing needs.
“When it came to the different growth areas, it really comes down to infrastructure and capacity, to be completely honest,” LaFayette said during the hearing.
Road work and paving projects are also expected this summer, though town officials are still finalizing which roads will be included.
Taylor said the town is waiting to hear whether it will receive a Class 2 paving grant worth $200,000. If awarded, the funding would be added to the $450,000 the town has already set aside in its capital improvement plan for paving this year.
Even with that funding, Taylor said Milton remains behind where it ideally should be.
“We should be realistically budgeting over a million dollars a year for paving in order to stay on a 10-year rotating process for resurfacing roads,” he said.
At this point, Taylor said roads in the Main Street and Westford Road area are among those that have been discussed, though final paving decisions had not yet been made as of Friday.
Meanwhile, work is also continuing in and around Bombardier Park.
Taylor said construction on the perimeter path in the park was paused during the winter but is expected to resume this season. The project is intended to create a more accessible walking route around the park.
Residents who use the Town Forest may also notice another recent improvement: a new ADA-compatible viewing platform along the trail system.
Taylor said the platform itself is complete, with signage recently installed. Seating and a picnic table are still expected to be added.
Additional infrastructure work is also expected at the town garage, where groundwork for a new salt shed could begin within the next few weeks.
Taylor said the structure is expected to be completed around August and will allow the town to better stockpile winter materials in advance of snow season.
“Our goal there is to be able to hold a complete season in one time,” Taylor said.
The shed is expected to hold about 2,000 tons of salt and roughly 4,000 tons of sand, which Taylor said would help the town better manage pricing and supply issues, especially after this year’s regional salt shortage.
Other visible changes may also be taking shape along Milton’s commercial corridors.
Taylor said residents may begin to see activity at the Dewey pile site across from the Milton Diner, as well as movement connected to future plans involving Bevin’s construction and DJ’s Tree Service.
He also said Pete’s RV is expected to begin site work along Route 7, where soil compression work is anticipated to begin.
“When they finally move into Milton, I’m very excited to have them in Milton,” Taylor said. “I think they’re going to be a little bit of an economic driver for us.”
Even the recently overhauled Exit 17 interchange is still seeing final touches.
Taylor said additional signage and lighting work is expected there in the coming days, much of it taking place overnight.
As several projects begin to move from plans on paper to visible construction, Taylor said this season reflects a broader period of growth and long-term planning for Milton.