MILTON — After years of planning and delays, the Town of Milton has formally entered into an agreement to lease land along Lamoille Terrace for the construction of a new solar array, marking a step toward the community’s renewable energy goals.
At its April 7 meeting, the Milton Selectboard voted unanimously to accept and enter into an Option and Lease agreement offered by Norwich Solar and Sea Oak Capital.
The agreement authorizes the development of a 500-kilowatt (AC) ground-mounted solar electric generating system on a portion of town-owned property at 145 Lamoille Terrace, near the wastewater treatment facility.
According to town documents, the system will include a variety of mechanical and electrical infrastructure — such as racking, solar modules, inverters, transformers, utility poles and overhead lines — and has already received approval from the Vermont Public Utility Commission.
The lease agreement marks the first major advancement in the project since 2023, when the site was initially approved as a preferred location. The project had remained largely inactive following that vote, pending final negotiations and legal review.
During an executive session on April 7, the selectboard met with Town Attorney Kirt Mayland and town officials to finalize legal details. Following that session, the board formally approved the lease.
Acting co-Town Manager John Bartlett said Norwich Solar, the company overseeing the project, stated the installation is now on track for completion by the end of 2025.
The solar array is designed to generate clean energy and help offset the town’s dependence on fossil fuels. The location — a parcel of land not suitable for traditional development — was chosen specifically for its proximity to existing public infrastructure and minimal environmental constraints.
The town's long-term effort to bring renewable energy to Milton dates back to 2014, when the project was first proposed. After an initial vendor filed for bankruptcy, the town pivoted and partnered with Norwich Solar to bring the initiative to completion.
Milton’s 2018 Comprehensive Plan calls for increased investment in renewable energy and energy efficiency, noting the financial and environmental benefits such projects can bring to residents and taxpayers.
As the project enters its installation phase, town officials say they will continue working with state agencies to ensure compliance with environmental and land use regulations.