MILTON — New paving is coming to portions of five Milton roads this year. 

The project includes resurfacing work on Bear Trap Road, Middle Road, Hunting Ridge Lane, Steeplechase Lane and Fox Run Lane.

The Milton Selectboard unanimously approved a contract for the work June 2. Frank W. Whitcomb Construction Corp. was awarded the contract with a bid of $565,957.50 — nearly $120,000 less than the engineer’s estimate of $682,420. The decision followed a public bid process and a review by town staff and engineering consultants from Stantec Consulting Services Inc.

“This is a good number,” Milton finance director Amber Baker said to the board. “The engineer’s estimate came in at $682,420, [but] it came in substantially less with the final bid from FW Construction.”

The funding for the project will come from the town’s Capital Improvement Plan for fiscal years 2025 and 2026, as well as $200,000 from a Class 2 Paving Grant.

While the board moved quickly to approve the resurfacing plan, selectboard member Leland Morgan asked how much of Bear Trap Road would be included in the upcoming work, noting that some sections had been resurfaced not long ago. Town officials did not immediately specify which portion of the road is scheduled for resurfacing.

Another road discussed — though not included in the upcoming resurfacing plan — was Sanderson Road, which has become a frequent source of complaints from Milton residents. Baker acknowledged the poor condition of the road and the town’s limited options.

"People have been calling and complaining about Sanderson Road,” Baker said. “We are very well aware of Sanderson Road and the condition that it's in. We don't have enough money to do it now, but we are hoping to do a portion of it next year.”

The selectboard approved the motion to award the contract to Frank W. Whitcomb Construction Corp. unanimously, following a motion from Morgan and a second from Clerk Brenda Steady.

In total, three companies submitted bids for the project. S.D. Ireland Brothers Corporation offered a bid of $590,206.50, and Pike Industries, Inc. submitted a bid of $595,340.25.

The resurfacing contract is the latest step in the town’s ongoing efforts to maintain Milton’s roadways through a combination of grant funding and capital improvement planning.

While major repairs for Sanderson Road are off the table for now, Baker said the town’s highway crew will complete some in-house work on the road this season to improve its condition until more substantial repairs can be budgeted.

A formal schedule for the FY26 resurfacing work is expected to be developed in coordination with Frank W. Whitcomb Construction and the Department of Public Works in the coming months.

The selectboard will next meet at 6 p.m. Monday, June 16 at the Milton Municipal Building.