MILTON — The Milton School Board voted May 22 to award contracts for long-planned roof and window repairs at the Herrick Avenue building, marking another step forward in the district’s effort to address aging infrastructure at the middle and elementary school.
After reviewing bids earlier this month, the board unanimously approved a $796,269 contract with Snow Country Roofing for roof replacement and a $1,556,939 contract with Glass Connection for window replacement, pending a required state bid waiver.
The district received four bids for the Herrick Avenue roof replacement project, with three meeting the district’s proposed construction timeline for this summer.
Board Vice Chair Jeremy Metcalf said MTSD buildings and grounds manager Bruce Cheeseman found no material differences in the proposed scopes of work among the qualifying bids.
On the recommendation of the district’s facilities committee, the board voted to award the contract to the lowest bidder, Snow Country Roofing.
Work is scheduled to begin after June 16, with a targeted completion date of Aug. 4.
Securing bids for the window replacement project proved more difficult. Although the district solicited four requests for bids, only one company — Glass Connection — submitted a proposal. Because state law typically requires at least three bids for large public projects, the district will apply for a bid waiver from the Vermont Agency of Education.
Pending state approval, the district plans to move forward with Glass Connection’s $1.56 million proposal, which involves the replacement of over 200 windows and installation of a new thermal door near the cafeteria.
Due to long lead times on materials and logistical concerns, the project will be completed in sections, likely during school breaks over the next year.
“We can break up the project in sections,” MTSD director of operations Matt Grasso said during the meeting. “So, you know, it can be weather dependent. You could do a wing in February, a section during April break, and then do the remainder next.”
Grasso noted the district has used Glass Connection previously for window work and he considers the company reliable.
Board members acknowledged the potential for additional expenses once work begins. Removing windows in an aging building may reveal issues like stucco damage or wood rot underneath existing frames.
“You’re gonna potentially have stucco repair,” Grasso said. “When they pull out windows, you may have some rotten wood under there as well.”
Superintendent Amy Rex also raised concerns about starting and completing portions of the project in colder months.
“I always think of what are some things that can go wrong in bad weather when dealing with windows,” Rex said. “When things are contracting and expanding… there’s more opportunity for accidents.”
The roof project will proceed with Snow Country Roofing next summer, while the window project’s timeline depends on state approval of the bid waiver and coordination with other planned summer work, including a stormwater management project at the Herrick site.
The bid approvals mark the latest chapter in the Herrick Facilities Project — a comprehensive, multi-year plan funded in part by an $8 million bond approved by Milton voters in March. The bond was designed to address infrastructure needs at the elementary and middle school building, including HVAC improvements, roof and window replacements, and other health and safety upgrades.
Further updates on project scheduling and approvals are expected at upcoming board meetings.