MILTON — The Milton School Board voted March 27 to take next steps in addressing long-standing infrastructure issues at the Herrick Avenue school building, approving thermal imaging of the roof and initiating the bid process for a large-scale window replacement.
Both efforts are part of the ongoing Herrick Facilities Project — a response to aging infrastructure at the Milton Elementary and Middle School complex. The project gained urgency last year after mold concerns delayed the start of school and displaced students from several classrooms.
These projects are funded in part by an $8 million bond approved by Milton voters on Town Meeting Day in March. The bond was designed to address major infrastructure needs at the Herrick Avenue complex, including roof and window replacements, HVAC improvements, and other health and safety upgrades.
Board members unanimously approved a $5,950 contract with IR Analyzers, Inc. to conduct an infrared and nuclear moisture analysis of the approximately 120,000-square-foot roof. The testing, often referred to as Vector Mapping, uses thermal imaging and a Troxler nuclear gauge to detect areas where insulation may be compromised due to moisture.
The results will guide the scope of necessary roof work — whether the district can repair targeted sections or if a full replacement is needed.
“We started looking at the roof on the Herrick Avenue building and windows, and then some legal requirements,” school board Vice Chair Jeremy Metcalf said during the meeting. “One of the things we saw as a recommendation is they can do a radar and sonar of the entire roof, and it would tell where insulation is bad.”
Metcalf noted state law requires any project between $40,000 and $2 million to be signed off by both a licensed architect and an engineer.
“One option is about $2 million to take the roof completely off and put it back on,” he said. “And then there are other options that are less if you just take the bad insulation off and replace just that.”
At the Facilities Committee meeting held earlier that same day, committee members reviewed estimates for traditional roof replacement — both full and partial — ranging from $1.2 million to $1.9 million, each offering a 20-year warranty.
A third option involves a silicone spray roofing system, a newer product that does not require removal of the existing roof. The estimated cost for that method is approximately $850,000, plus any necessary base layer installation. It also carries a 20-year warranty and claims improved energy efficiency.
The Facilities Committee recommended the school board:
Approve the Vector Mapping contract.
Begin prequalification of contractors for roof work.
Depending on test results, proceed with traditional roof replacement.
The board also voted to move ahead with the bidding process for the replacement of 242 windows and three front sections of the Herrick building.
The project is currently estimated at $1.5 million.
Because the project falls under the $2 million threshold, the district is not legally required to prequalify vendors. During the Facilities Committee meeting, members discussed fiberglass versus aluminum window systems. Fiberglass offers strong insulation value, while aluminum — which includes thermal breaks — is more cost-effective and widely available.
The committee recommended using aluminum and advised the board to proceed to bid without prequalification.
All motions — to approve the Vector Mapping contract, begin the roof prequalification process, and open bidding for the window project — passed unanimously.
The roof testing must be conducted at night and under dry weather conditions. IR Analyzers will provide a detailed report, including thermographic imagery and AutoCAD-style drawings, to identify areas of concern. The results will help the district finalize the scope and method of roof replacement.
“We could then make a scope of work plan based on what we find,” Metcalf said. “They would kind of give us some direction to go.”
The Herrick Facilities Project remains ongoing, with further decisions expected by board members in the coming months as testing results are completed and contractor bids are reviewed.