Milton moves ahead with $1.2M salt shed project at DPW facility

Posted

MILTON — After years of planning, the Town of Milton is moving forward with the final major component of its Public Works campus, a new 14,300-square-foot salt shed.

The selectboard on Oct. 6 unanimously approved awarding the construction management contract to Connor Construction Inc. and authorizing $1.23 million in funding to build the structure at the Don Turner Jr. Public Works Facility on Bombardier Road.

Town officials said the project will be financed using a mix of impact fees ($368,895), remaining funds from the DPW facility project ($522,278) and the town’s general fund balance ($338,447).

Why a new shed is needed

The new salt shed will replace the outdated Ice House property currently used for salt storage. Highway superintendent Eric Gallas said the Ice House site has long been a temporary solution and no longer meets the town’s needs.

“Once this structure is in place,” he said, “we’re going to be able to hold an entire season's worth of salt.” 

When the new salt shed is complete, the town will no longer have to split operations between the Ice House and DPW facility – a setup said to create inefficiencies and salt shortages. Consolidating everything on one site will streamline operations, improve safety and protect materials from weather-related damage Gallas said. 

Town officials said the new shed also completed the DPW campus as originally envisioned, bringing all public works functions under one roof. 

Cost savings and timeline

Construction is expected to begin this spring, with the town’s own public works crew completing site preparation work this winter to save an estimated $250,000.

Gallas told the board that self-funding the project now — instead of waiting to use a $500,000 federal grant — will ultimately save money in the long run. Using the grant would raise costs by about $100,000 immediately, he said, and delaying construction until 2027 could increase expenses by as much as $600,000 due to inflation and new building requirements.

“By waiting to utilize the grant, it actually is going to cost us $100,000 more,” Gallas said. “In two years, it equates to $600,000.”

Town Manager Chris Taylor agreed, saying the delay and added requirements tied to the grant made it an unreliable option.

“If we wait, there’s no guarantee that [the grant project] will ever come to fruition without self-funding it,” Taylor said. “It’s an unfortunate pattern that we’ve started to see with grants lately. We’ve had a couple already that we have not been able to utilize due to the stipulations put behind them.”

Choosing Connor Construction

Connor Construction previously served as project manager for the DPW facility, which opened earlier this year. Taylor said bringing them back ensures continuity, accountability and technical oversight for the complex building process.

“The important part is, we have a path forward for the funding,” Taylor said.

Gallas said the town’s public works staff are experienced in civil work but not structural construction, and outsourcing project management reduces risk.

“The town staff has some skills—the earthwork side of things, we’re well skilled up,” Gallas said. “But when it comes to laying out a building... if you’re off by a centimeter, the cost to rectify something like that would be huge. We are well-versed in civil construction. We are not builders, and nor do we want to be.”

Funding breakdown and rationale

Selectboard clerk Brenda Steady questioned the breakdown of construction management fees and why the town was selecting a more expensive option.

Gallas said the fee covers coordination of subcontractors, quality control and liability for project errors. 

“The more subs being coordinated, the larger the management fee,” he explained. “That fee covers assuming project risk and ensuring the work is done right.”

Taylor said the town’s fund balance remains healthy even after this spend.

While the board hoped to start construction this winter, Gallas said timing and weather constraints mean the current season will proceed under existing arrangements.

For one more winter, the DPW will continue storing salt at both the Ice House property and the current facility. Once the new structure is complete, the town plans to decommission the Ice House site entirely.

“That’s the last build-out of the infrastructure for the facility,” Gallas said. “We can make it work for another season, get this in and not have to worry about any salt shortages like we had a couple years ago.”