MILTON — Three months into construction, Milton's Hourglass Project is beginning to look less like site preparation and more like a new roadway taking shape.
Fresh pavement now covers portions of Middle Road, Whisper Lane and Keelty Crossing, while construction has shifted north along U.S. Route 7 as crews begin rebuilding another section of the highway.
According to the Vermont Agency of Transportation, contractors spent the week of July 7 milling pavement, removing sections of the existing roadway and installing new roadway structures between the area near Subway and the shopping plaza. Drivers traveling through the corridor also encountered temporary one-way traffic controlled by flaggers while work progressed.
The latest work follows several weeks of construction focused on Middle Road and Railroad Street, where crews completed fine grading and paving while continuing preparation for new sidewalks and underground drainage infrastructure.
As construction advances, VTrans says motorists should continue to expect changing traffic patterns, construction equipment and occasional flaggers throughout the project area. Drivers are encouraged to slow down, pay attention to posted signs and allow extra travel time when traveling through the work zone.
The $6.76 million project will reconfigure the intersections of U.S. Route 7, Middle Road and Railroad Street, replacing the existing intersections with a new roadway network designed to improve traffic flow and safety through Milton's village center.
Plans call for installing new traffic signals and mast arms, adding turn lanes along Route 7, constructing new roadway connections between Railroad Street and Route 7, and building new sidewalks to improve pedestrian access.
Currently, the Route 7, Middle Road and Railroad Street intersection operates as a three-way stop-controlled intersection. Under the new design, the existing intersections with Route 7 will be eliminated and replaced with two new road segments connecting Middle Road and Railroad Street to the highway.
Construction began this spring and is expected to continue through summer 2027.
Residents can sign up to receive weekly construction updates through the Vermont Agency of Transportation.