COLCHESTER — Drivers moving through the Exit 17 interchange this week will notice a significant amount of visible progress as the long-running reconstruction project enters what appears to be its most polished phase yet.
The Vermont Agency of Transportation announced new lane reductions and traffic shifts on U.S. Route 2 and U.S. Route 7, continuing through Friday, Nov. 21. Two-way traffic will remain open, but motorists should expect changing patterns throughout the work zone between the Shell gas station and Wiley Road on U.S. 7, and between Jasper Mine Road and Chimney Corner on U.S. 2.
According to VTrans, crews began installing permanent pavement markings over the weekend and will continue that work throughout the week, weather permitting. Installation of permanent roadway signage across the project area is also underway and is expected to remain a major focus over the next several days.
This phase of work marks another visible milestone in the $31.7 million reconstruction of the Interstate 89 Exit 17 interchange, one of the state’s most complex transportation projects.
The project, which began in spring 2024, includes a full replacement of the U.S. Route 2 bridge over I-89, a rebuilt southbound off-ramp and a new southbound on-ramp, an extended northbound deceleration lane, and expanded turning capacity on both U.S. 2 and U.S. 7 to reduce backups at Chimney Corner.
Much of that heavy construction has already been completed.
Local officials have noted in recent Milton Selectboard meetings that work appears to be tracking ahead of schedule, though VTrans has not updated its official timeline.
The agency’s website continues to list summer 2026 as the projected completion date. Still, the increasingly finished look of the interchange — including new lanes, rebuilt ramps and ongoing pavement striping — suggests drivers may see more of the end result taking shape over the next few months.
The project area stretches from just east of Jasper Mine Road to the U.S. 2/7 intersection, and from Simon’s Chimney Corner Store north to Wiley Road. Construction is being completed by Kubricky–Jointa Lime LLC, with design work by VHB, and is funded entirely through federal highway programs.
VTrans issues weekly construction updates and real-time traffic alerts during the active construction season. Residents and commuters can sign up for notifications or submit questions by emailing info@ColchesterExit17.com or calling the 24-hour hotline at 802-595-4399.