Champlain Water District to fully shut down treatment plant April 16

Posted

CHAMPLAIN WATER DISTRICT — CWD will shut down its water treatment plant Wednesday, April 16, from 8 a.m. to 6 p.m. as necessitated by an ongoing construction project at the plant. 

The treatment plant shutdown will be full and comprehensive. In light of its temporarily scheduled plant dormancy, CWD is requesting all of its customers curb all non-essential water use, including both indoor and outdoor usage — dishwater, laundry, hoses and beyond. 

Collective efforts to conserve water tomorrow will allow CWD to maintain adequate storage volumes and fire protection in the water storage tanks located throughout Chittenden County. 

Fire departments are reminded to call CWD about any fires or other water related emergencies, and municipal water systems are asked not to perform hydrant flushing or fire flow testing. 

Affected water systems are in Essex Town, Essex Junction, Milton, Colchester fire district No. 1, Colchester fire district No. 3, Colchester Town, Winooski, Williston, South Burlington, Shelburne, the Village of Jericho and the Malletts Bay Water Company. 

The precise reason for the construction behind the shut-down is based on a need to replace CWD’s one-million-gallon south filter water tank, which has some structural problems. A north tank was also installed in 2016. 

The original hope was that with the second tank, they’d be able to do the maintenance the original tank required without disrupting the flow of filtration — but it wasn’t that simple. 

“We need to cut in a new valve, because the way things are currently set up, you can't isolate the [northern] second tank that was put in 2016,” said Joe Duncan, general manager of CWD. 

Through tomorrow’s work, the issue of isolating the tanks flow from one another should be resolved — with the plan for the day being to put in a new line to separate the two tanks to prevent future full-system shutdowns when the tanks need servicing in the future. 

“The goal was to take [the south tank] out of service and fix it,’ Duncan said. “Unfortunately, we realized the tank was not structurally sound anymore after being able to finally get into it.” 

“Structurally, that tank was failing to the point where we were trying to make any investments in it, we'd be pretty close to being in a new tank,” he added. “So we decided we'll take it offline and completely remove it and put in a brand new one.” 

The process for filtering water through the failing tank up to this point was to do an additional dose of chlorine filtration beyond the usual protocol, in order to kill off any remaining bacteria or microorganisms the south filter should have caught. 

Periodic updates will be posted about project status and the readiness of a return to normal facility operations on champlainwater.org. Those with further questions may contact CWD.